The
kit is made up of 3 main components
1. Top unit (comprising a top fixing & cable holder)
2. 4m cable with soldered ends
3. Base unit (comprising a base fixing, tensioner & a cable
holder)
Fit four connectors (X9000V)
onto one of the the acrylic
shelves
Measure the distance between the cable centers.
Having decided where the shelves are to be sited in your space, mark on
the ceiling the appropriate positions for the top of the cables. Screw
the top fixings into the ceiling and screw on the cable holders. Using
a plumb line make corresponding marks on the floor and screw the base
fixing to the floor.
Taking the total measurement from ceiling to floor LESS 20/25mm, cut
the cable. Push the CUT end into the top cable holder and the soldered
end into the bottom cable holder. Using the tensioner attach the bottom
cable holder to the base fixing and tension the cable.
Attach shelves as required.
|